Removing MagAO-X from the Telescope

This procedure describes how to remove the MagAO-X instrument on the Magellan Clay Telescope.

Estimated Time to Complete: 2 hours

This document can be downloaded as a PDF: Removing MagAO-X from the Telescope

Initial Conditions

  • Instrument on Magellan Clay Nasmyth Platform, operating.

Shutdown

  • At the end of the last night, have the TO position the telescope so that the NASE platform faces the elevator.

  • Power down all of MagAO-X

    • Ensure that stagepickoff in the out position.

    • Place the k-mirror at 0 degrees.

    • Select the Ha-narrow and CH4-875 filters on fwsci1/2

    • turn off power for all devices on MagAO-X following the regular shutdown procedure.

    • use the shutdown -h now command to halt both RTC and ICC

    • once the computers are off, turn off all things in the rack.

  • Remove blower hose and cover the hole.

  • Remove all cables

    • See detailed procedure for removing 2K DM cables

  • Electronics Rack

    • Ensure that roll-out shelves are restrained

    • Close and lock doors

    • Tape keys down

  • Instrument

    • Remove eyepiece

    • Remove bumpers and pusher hardware

    • Remove air connection

    • Tape over any exposed holes (from cables, etc)

    • Secure any loose cables

    • Shrink wrap the instrument

    • Install solar blanked over shrink wrap

  • Cart and Rigging

    • Verify all cart hardware is in-hand

    • Verify two wire harnesses are in hand

Rig Onto Cart

  • Lower table legs onto the casters by turning the 16 leveling bolts, and remove the metal pads

  • Roll the instrument away from the telescope

  • Assemble the cart around the instrument

    • CAUTION: be careful to not bump the legs with the cart

  • Ensure that the 8 large bolts on the cart are snug but not tight

  • Attach the lifting wire-harness to each side of the cart

  • Attach the load spreader with straight extensions to the crane, using a crane scale

    ../_images/load_spreader_attach.jpg

    The load spreader attached to the crane for lifting the cart

  • Place the load spreader in the center position (the cart is symmetric)

  • Lift the load spreader, and position it over the instrument

  • Being careful to not bump the instrument, lower the load spreader and attach the lifting harness D rings. Use 3x shackles to extend the length to reach the cart on the floor.

    ../_images/cart_lift_extensions.jpg

    Lifting harnesses attached with shackle extensions

  • Position a person at each corner of the cart

    CAUTION: Do not allow the cart to bump the legs or the table uncontrolled

  • Slowly lift the cart (320 lbs) until it is touching the bottom of the table

    ../_images/cart_lift_tofrom_table.jpg

    The cart being lifted to the bottom of the table.

  • Install the 4 bolts attaching the cart to the table. Use only the 4 outboard bolts. Loosen bolts on the cart as needed to adjust.

  • Once the cart is bolted to the table bottom, while 320 lbs is still on the crane, tighten all cart bolts. Do not over-tighten, make 1/4 turn after the washers are no longer free. This is to avoid excessive stress on the table.

  • Install the triangle stabilizing ropes between the crane hook and

  • Reposition the load spreader center to the instrument + cart position marked on it.

    the lifting fixture IAW the below figure. Tighten, but do not cause them to pick the load.

    ../_images/stabilizers.jpg

    The triangle stabilizing ropes should be tight, but not become the lifting point for the load.

  • Ensure that there is room to move the legs out from under the table towards the telescope.

  • Position a person at each end of the cart to stabilize it during the lift.

  • Position two people to remove the legs from under the table

  • Lift the table off the legs.

  • Move the legs out from under the table.

    ../_images/cart_lift_legs_ready.jpg

    The cart and instrument ready to be set down on the wheels, with legs out of the way.

  • Set the cart down on its wheels.

  • Move MagAO-X onto the elevator, and remove from the dome

  • When cart is on concrete outside Clay, move very slowly to avoid excessive vibration

Transport MagAO-X To The Clean room

  • Ensure that the lift gate at the summit has been adjusted for slow smooth operation as is done for the asm

  • Push MagAO-X onto the lift-gate

  • Raise the lift-gate to the height of the flatbed truck

  • Move MagAO-X onto the truck, using the come-along

    ../_images/inst_backed_up.jpg

    MagAO-X is loaded at the telescope using the lift gate, adjusted for slow operation.

  • Secure the instrument by strapping the cart down at 4 points as illustrated in the below figure.

    ../_images/inst_on_truck.jpg

    MagAO-X will be strapped to the Isuzu.

  • Slowly drive the truck to the cleanroom

  • Back the flatbed truck up to the lift gate.

  • Next, using the come-along, carefully move MagAO-X onto the lift gate.

  • Return to the top with the flatbed and move the legs to the cleanroom.

  • Placed on 2 dollies as in the below image.

    ../_images/legs_dollies.png

    Legs on 2 dollies placed in the middle of the table under each lower long tie bar (away from basket).

  • Move the legs to the flatbed and strap them down.

    ../_images/legs_truck.png

    Legs strapped to the truck.

Transport Electronics

  • remove the earthquake bar

  • Move the rack to the lift gate, and load it on the pickup.

  • place foam between the rack side and the truck to protect cable connectors

    ../_images/rack_connectors.jpg

    The electronics rack has many delicate connectors on the side.

  • strap the rack securely to the truck

    ../_images/electronics_pickup.jpg

    The rack on a truck for transport.

  • drive the truck to the cleanroom

  • unload the rack using the lift gate

Remove AOC from Control Room

  • power down AOC

  • remove monitors and pack

  • move AOC to cleanroom.